18 men can do a piece of work in 10 days.They have worked to gether for 4 days.If the remaining work has to be completed by 4 days, then how many men more are required? ???
in Word Problem Answers by

Your answer

Your name to display (optional):
Privacy: Your email address will only be used for sending these notifications.
Anti-spam verification:
To avoid this verification in future, please log in or register.

1 Answer

werk tu du=18*10=180 man-daes

18 men werk 4 daes=72 man-daes

tu du=180-72=108 man-daes

tu du 108 in 4 daes, yu need 108/4=27men

but oenlee if all werk good & stae the full 4 daes

This assume that krowd kan werk witout stumbel over eech other
by

Related questions

1 answer
asked Dec 1, 2016 in Word Problem Answers by anonymous | 583 views
0 answers
asked Oct 12, 2019 in Word Problem Answers by anonymous | 970 views
1 answer
asked Jan 8, 2019 in Word Problem Answers by tajlen | 1.0k views
1 answer
asked May 31, 2017 in Word Problem Answers by Maria | 1.2k views
1 answer
asked Mar 31, 2015 in Word Problem Answers by anonymous | 665 views
1 answer
asked Apr 25, 2014 in Algebra 2 Answers by omgamberword Level 1 User (240 points) | 551 views
1 answer
1 answer
1 answer
asked Sep 8, 2012 in Word Problem Answers by anonymous | 781 views
Welcome to MathHomeworkAnswers.org, where students, teachers and math enthusiasts can ask and answer any math question. Get help and answers to any math problem including algebra, trigonometry, geometry, calculus, trigonometry, fractions, solving expression, simplifying expressions and more. Get answers to math questions. Help is always 100% free!
87,516 questions
100,279 answers
2,420 comments
733,106 users