Arun, Kartik and Mira can do a work in 90, 30 and 45 days respectively. If they work together, in how many days will they complete work?

by

Your answer

Your name to display (optional):
Privacy: Your email address will only be used for sending these notifications.
Anti-spam verification:
To avoid this verification in future, please log in or register.

1 Answer

Their rates of working are:

Arun: 1/90; Kartik: 1/30; Mira: 1/45 of the work per day.

Working together then can complete:

1/90+1/30+1/45=1/90+3/90+2/90=6/90=1/15 of the work in a day.

So it would take them 15 days to complete the work together.

Let's check the result. In 15 days Arun would be able to do ⅙ of the work, Kartik ½ the work, and Mira ⅓ the work. ⅙+½+⅓=1, so all the work would be completed in 15 days.

by Top Rated User (1.2m points)

Related questions

1 answer
asked Sep 4, 2013 in Other Math Topics by anonymous | 747 views
1 answer
Welcome to MathHomeworkAnswers.org, where students, teachers and math enthusiasts can ask and answer any math question. Get help and answers to any math problem including algebra, trigonometry, geometry, calculus, trigonometry, fractions, solving expression, simplifying expressions and more. Get answers to math questions. Help is always 100% free!
87,516 questions
100,279 answers
2,420 comments
731,375 users