It could take kamau working alone 30 days,wanyonyi 40days and matano 60days to complete digging a shamba,all the three start working together but 5days later kama falls sick and can not continue.Determine how many more days it would take wanyonyi and matano to complete the work
in Word Problem Answers by

Your answer

Your name to display (optional):
Privacy: Your email address will only be used for sending these notifications.
Anti-spam verification:
To avoid this verification in future, please log in or register.

1 Answer

by Level 10 User (57.4k points)

Related questions

Welcome to MathHomeworkAnswers.org, where students, teachers and math enthusiasts can ask and answer any math question. Get help and answers to any math problem including algebra, trigonometry, geometry, calculus, trigonometry, fractions, solving expression, simplifying expressions and more. Get answers to math questions. Help is always 100% free!