25 men finish a work in 14 days,how many days are required for 35 men to finished the same work.
asked Nov 22, 2016 in Other Math Topics by sajoo

Your answer

Your name to display (optional):
Privacy: Your email address will only be used for sending these notifications.
Anti-spam verification:

To avoid this verification in future, please log in or register.

1 Answer

More men take less time so we want 25/35 of 14=5/7*14=10 days.
answered Nov 22, 2016 by Rod Top Rated User (442,460 points)
Welcome to MathHomeworkAnswers.org, where students, teachers and math enthusiasts can ask and answer any math question. Get help and answers to any math problem including algebra, trigonometry, geometry, calculus, trigonometry, fractions, solving expression, simplifying expressions and more. Get answers to math questions. Help is always 100% free!
78,526 questions
82,365 answers
1,903 comments
63,405 users